SHAYONA ORNATEMahaRERA P49600000035

by SHAYONA DEVELOPERS

SURVEY NO 77/1 , 77/2/1 , 85/1 AND 85/2, SILVASSA, 396230

Mar 2028
Possession
118.6%
Built
0
Complaints
52
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Dec 2021, now proposed Mar 2028 per the RERA filing.

Official RERA facts

Registration
P49600000035
Status
Ongoing
Stage
Certificate Signed
Possession
March 2028originally December 2021
Construction
118.6% complete
Units sold
40 of 52

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lighting10%
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving station25%

Building & registration

RERA registered
Nov 2017
Floors
6
Unit mix
52 res ยท 0 comm
Architect
DIVINE ENGINEERING AND PLANNING CONSULTANCY

Buyer community

Connect with other buyers and owners of SHAYONA ORNATE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHAYONA ORNATE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.