SHAYONA ORNATEMahaRERA P49600000035
SURVEY NO 77/1 , 77/2/1 , 85/1 AND 85/2, SILVASSA, 396230
Mar 2028
Possession
118.6%
Built
0
Complaints
52
Units
High risk
- Possession delayed ~6 yrs. Originally promised Dec 2021, now proposed Mar 2028 per the RERA filing.
Official RERA facts
- Registration
- P49600000035
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2028originally December 2021
- Construction
- 118.6% complete
- Units sold
- 40 of 52
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lighting10%
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving station25%
Building & registration
- RERA registered
- Nov 2017
- Floors
- 6
- Unit mix
- 52 res ยท 0 comm
- Architect
- DIVINE ENGINEERING AND PLANNING CONSULTANCY
Buyer community
Connect with other buyers and owners of SHAYONA ORNATE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SHAYONA ORNATE. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.