J9 TRITONMahaRERA P49600000111

by FOUR SEASONS LIFE SPACE

SURVEY NO 182/1/8/1/1, SILVASSA, 396230

Dec 2026
Possession
41.8%
Built
0
Complaints
116
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 41.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P49600000111
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
41.8% complete
Units sold
29 of 116

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply52%
Sewerage (Chamber, Lines, Septic Tank , STP)52%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jul 2021
Floors
11
Unit mix
0 res ยท 116 comm
Architect
TEJAS M SHUKLA

Buyer community

Connect with other buyers and owners of J9 TRITON โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching J9 TRITON. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.