SHANKAR PLAZAMahaRERA P49900011123

by PRASHANT MANOHAR NIKAM

2407,2510, Amalner (M Cl), 425401

Mar 2021
Possession
27.3%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~1 yr. Originally promised Dec 2019, now proposed Mar 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Mar 2021) has passed with construction at 27.3%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Mar 2021 per the RERA filing.

Official RERA facts

Registration
P49900011123
Status
Ongoing
Stage
Certificate Signed
Possession
March 2021originally December 2019
Construction
27.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths5%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
4

Buyer community

Connect with other buyers and owners of SHANKAR PLAZA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.