Under construction

MUNDADA ESTATEMahaRERA P49900030529

by AMEY OMPRAKASH MUNDADA

Amalner 1797-1 Plot No 27 To 104, Amalner, 425401

Dec 2023
Possession
50.7%
Built
0
Complaints
78
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 50.7%.

Official RERA facts

Registration
P49900030529
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
50.7% complete
Units sold
0 of 78

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)75%
Storm Water Drainsnot started
Landscaping & Tree Planting50%
Street Lighting75%
Community Buildings50%
Water conservation /Rain water harvesting50%
Electrical meter room, sub-station, receiving station50%

Building & registration

RERA registered
Aug 2021
Floors
2

Buyer community

Connect with other buyers and owners of MUNDADA ESTATE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MUNDADA ESTATE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.