Plot No 26 Survey No 154, Anand Nagar, 443201
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2026 per the RERA filing.
Official RERA facts
- Registration
- P50000078469
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2026originally March 2026
- Construction
- 79.5% complete
- Units sold
- 9 of 15
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Possession extension history
- EA08052620883Revised to September 2026
As certified by the Architect in Form-1 for last quarter, submitted as part of Quarterly Progress Reports, majority of the construction work of the project is completed and balance finishing work is in progress. We are hopeful that the balance work will get completed in couple of months and few months thereafter are required for obtaining various NOCS as well as Occupation Certificate for the project. In view of the above, we request this Hon’ble Authority to grant extension to the project registration until 30/09/2025
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Dec 2024
- Floors
- 6
- Unit mix
- 15 res · 0 comm
- Architect
- AR Architect Rajput
- Plot / CTS / survey no.
- Plot No 26 Survey No 154
- Planning authority
- Chikhali Municipal Council
- Approved layout land
- 297 sq.m
- Land for this registration
- 297 sq.m
- Recreational open space
- 0 sq.m
- Permissible built-up area
- 1,122.66 sq.m
- Registered office
- Vidya Vihar
- North
- Plot No 25
- South
- Plot No 27
- East
- 10 Ft Service Road
- West
- Layout Road
Project bank account
The RERA-designated account this project's payments should go to — verify before wiring any money.
- HDFC BANK — 48680IFSC HDFC0000221SETHI HEIGHTS,OPP ZILLA PARISHADAKOLAMAHARASHTRA444001
Commencement Certificate documents
- 6_CC.pdf
Buyer community
Connect with other buyers and owners of Krushna Skyline — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet — start one and connect with the next buyer researching Krushna Skyline. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.