Under construction
PARIKRAMA GREENSMahaRERA P50300011577
by NITIN JUGALKISHOR CHENDULKAR
56/1,01, AMRAVATI, 444606
Jun 2029
Possession
36.4%
Built
0
Complaints
162
Units
High risk
- Possession delayed ~4 yrs. Originally promised Jun 2025, now proposed Jun 2029 per the RERA filing.
Official RERA facts
- Registration
- P50300011577
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2029originally June 2025
- Construction
- 36.4% complete
- Units sold
- 63 of 162
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)35%
Storm Water Drainsnot started
Landscaping & Tree Planting15%
Street Lighting30%
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Space50%
Open Parking50%
Building & registration
- RERA registered
- Aug 2017
- Floors
- 10
- Unit mix
- 64 res ยท 98 comm
Buyer community
Connect with other buyers and owners of PARIKRAMA GREENS โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching PARIKRAMA GREENS. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.