PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

VARAD ENCLAVEMahaRERA P50300017220

by SUMANGAL ASSOCIATES

PLOT NO. 29A, 29B, 30A, SURVEY NO. 52-PART, 444601

Dec 2022
Possession
11.8%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 11.8%.

Official RERA facts

Registration
P50300017220
Status
New
Stage
Certificate Signed
Possession
December 2022
Construction
11.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jul 2018
Floors
5

Buyer community

Connect with other buyers and owners of VARAD ENCLAVE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VARAD ENCLAVE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.