Under construction

MADAN RATAN CITYMahaRERA P50500001473

by EMAAR DEVELOPERS & BUILDERS PVT LTD

CITY SURVEY NO. 39 KH NO 21/1, MOUZA CHIKHALI KHURD HOUSE NO 4714/ 1, BHOLE NAGAR, NAGPUR 440024, Nagpur (M Corp.), 440032

Dec 2026
Possession
61.2%
Built
0
Complaints
349
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Jun 2021, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P50500001473
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally June 2021
Construction
61.2% complete
Units sold
191 of 349

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths85%
Water Supply25%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains50%
Landscaping & Tree Planting70%
Street Lighting55%
Treatment And Disposal Of Sewage And Sullage Water25%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting25%
Energy managemcntnot started
Fire protection and fire safety requirements55%
Electrical meter room, sub-station, receiving station35%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Entrance Gate and Security Cabin85%

Building & registration

RERA registered
Jul 2017
Floors
8
Unit mix
268 res ยท 81 comm

Buyer community

Connect with other buyers and owners of MADAN RATAN CITY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MADAN RATAN CITY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.