PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Classic AkshayMahaRERA P50500005480

by Chourangi Builders and Developers Private Limited

Plot No. 159 Part, 163 Part, 164 part, 162 Part, Khapri, 441108

Dec 2032
Possession
0%
Built
0
Complaints
150
Units
High risk
  • Possession delayed ~10 yrs. Originally promised Dec 2022, now proposed Dec 2032 per the RERA filing.

Official RERA facts

Registration
P50500005480
Status
Ongoing
Stage
Certificate Signed
Possession
December 2032originally December 2022
Construction
0% complete
Units sold
31 of 150

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
12
Unit mix
91 res ยท 59 comm

Buyer community

Connect with other buyers and owners of Classic Akshay โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Classic Akshay. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.