PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Vyankatesh City 4MahaRERA P50500007447

by VYANKATESHA BUILDERS AND DEVELOPERS

Kh No 141,142,146/1, Kalamana, 440000

Jul 2023
Possession
25.3%
Built
1
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jul 2023) has passed with construction at 25.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2023 per the RERA filing.

Official RERA facts

Registration
P50500007447
Status
Ongoing
Stage
Certificate Signed
Possession
July 2023
Construction
25.3% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths20%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingdone
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
76

Buyer community

Connect with other buyers and owners of Vyankatesh City 4 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Vyankatesh City 4. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.