SIDDHIVINAYAK
7/8, Nagpur (M Corp.), 440009
- Possession date passed. The proposed possession date (Jul 2018) has passed with construction at 38.2%.
Promoter
Builder profile
View the promoterβs full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P50500007623
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- July 2018
- Construction
- 38.2% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Aug 2017
- Floors
- 6
- Plot / CTS / survey no.
- 7/8
- Planning authority
- Others
- Approved layout land
- 542 sq.m
- Land for this registration
- 542 sq.m
- Permissible built-up area
- 704 sq.m
- Registered office
- SIDDHIVINAYAK
- North
- PLOT NO
- South
- PLOT NO 9
- East
- EAST ROAD
- West
- LAY OUT OF OTEHER SOCIETY
Project bank account
The RERA-designated account this project's payments should go to β verify before wiring any money.
- CANARA BANK β 29783IFSC CNRB0001084BADKAS CHOUK MAHAL NAGPUR
Buyer community
Connect with other buyers and owners of SIDDHIVINAYAK β compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet β start one and connect with the next buyer researching SIDDHIVINAYAK. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.