Under construction

Bloomdale Row House 6MahaRERA P50500007914

by Mahindra Bebanco Developers Limited

17 Part 18 Part 19 Part 26 Part 27 Part 28 29 Part 30 Part 31 Part 35 Part 36 Part 39 Part, Khapri, 441108

Nov 2019
Possession
81.8%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Nov 2019) has passed with construction at 81.8%.

Official RERA facts

Registration
P50500007914
Status
Ongoing
Stage
Certificate Signed
Possession
November 2019originally November 2018
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths78%
Water Supply76%
Sewerage (Chamber, Lines, Septic Tank , STP)67%
Storm Water Drains63%
Landscaping & Tree Planting53%
Street Lighting58%
Community Buildingsdone
Water conservation /Rain water harvesting53%
Fire protection and fire safety requirements71%
Electrical meter room, sub-station, receiving station71%
Aggregate area of recreational Open Space58%
Open Parking65%
CCTV system in Common Area30%
Childrens play Areadone
Half Basket ball courtdone
Tennis courtdone
Power Back through DGdone
Sub Station Work65%
Swimming pooldone

Building & registration

RERA registered
Aug 2017
Floors
2

Buyer community

Connect with other buyers and owners of Bloomdale Row House 6 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Bloomdale Row House 6. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.