Under construction

KASTURI SQUAREMahaRERA P50500008255

by SKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD.

62/2, Gotal Panjari, 441108

Aug 2019
Possession
57.3%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Aug 2019) has passed with construction at 57.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2019 per the RERA filing.

Official RERA facts

Registration
P50500008255
Status
New
Stage
Certificate Signed
Possession
August 2019
Construction
57.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
LIFT WITH POWER BACKUP20%

Building & registration

RERA registered
Aug 2017
Floors
5

Buyer community

Connect with other buyers and owners of KASTURI SQUARE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching KASTURI SQUARE. Real notes from real buyers beat any brochure.

Start a discussion