PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SHALWAK ELITEMahaRERA P50500010251

by SHALWAK INFRABULLS

Plot no.11,corporation house no.190,CTS NO.358,Sheet No.34, Nagpur (M Corp.), 440012

Jun 2018
Possession
90.9%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2018) has passed with construction at 90.9%.

Official RERA facts

Registration
P50500010251
Status
Ongoing
Stage
Certificate Signed
Possession
June 2018
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains30%
Water conservation /Rain water harvesting40%
Fire protection and fire safety requirementsdone
Open Parking60%

Building & registration

RERA registered
Aug 2017
Floors
8

Buyer community

Connect with other buyers and owners of SHALWAK ELITE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHALWAK ELITE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.