All RERA projects
๐๏ธ
Under construction
Govind EnclaveMahaRERA P50500013663
Plot No 79 to 86 97 to 112 120 to 127 CTS Survey No 91/1 Mouza Hazari Pahad, ., 440006
Feb 2020
Possession
80%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~2 yrs. Originally promised Feb 2018, now proposed Feb 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Feb 2020) has passed with construction at 80%.
Official RERA facts
- Registration
- P50500013663
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- February 2020originally February 2018
- Construction
- 80% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply30%
Sewerage (Chamber, Lines, Septic Tank , STP)65%
Storm Water Drains65%
Water conservation /Rain water harvesting75%
Fire protection and fire safety requirements75%
Electrical meter room, sub-station, receiving station50%
Open Parking75%
Building & registration
- RERA registered
- Oct 2017
- Floors
- 6
Buyer community
Connect with other buyers and owners of Govind Enclave โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Govind Enclave. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.