PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

ANURAG ORCHIDMahaRERA P50500045638

by ANURAG DEVELOPERS

Plot No. 11, Khs. No. 107/3-7 & 107/4, Near Dhyandeep Convet SRPF Gate No 3 Jaitala, 440036

Dec 2025
Possession
49.5%
Built
0
Complaints
7
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 49.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2025 per the RERA filing.

Official RERA facts

Registration
P50500045638
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
49.5% complete
Units sold
5 of 7

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started

Building & registration

RERA registered
May 2022
Floors
8
Unit mix
7 res ยท 0 comm
Architect
Arya Vertex

Buyer community

Connect with other buyers and owners of ANURAG ORCHID โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ANURAG ORCHID. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.