Mangala Estate
187/1/1/1, Pawangaon, 441104
- Possession delayed ~7 yrs. Originally promised Jan 2024, now proposed Dec 2030 per the RERA filing.
Official RERA facts
- Registration
- P50500049268
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2030originally January 2024
- Construction
- โ
- Units sold
- 39 of 99
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Possession extension history
- EXT50500019049Revised to January 2025
We had registered the project mangala estate in February 2023 and have completed around 75% of the work as well in the said project. And my Rera team from the office have registered with a deadline of less than a year by mistake they selected 2024 instead of 2025 This was a typo error by my team. No promoter will set such a short deadline for a new project. I got to know this only after the registration certificate was generated. I have also tried the application for change but they have directed to use the extension module. And for such typo error we have to pay such a high fees in extension module . It is demoralising for a promoter. My desired completion date from the start was 30/1/2025. If I can get this extension I will be able to complete the entire project and sell it as well. Please consider it as it is not possible to complete such a big project in such a short time this is an honest mistake and I have also updated the project quarterly. Please consider it as it as an honest mistake and I am sorry for it. Only electrification, STP and paver block placement is left. Which will be completed 100% by 30/01/2025.
- EA12052620938Revised to December 2030
I, Shri Raju Laxmikant Itkelwar, prop. of the said project, am writing to formally request an extension for the completion date of our plotted development project located at Kh. No. 187/1/1/1, P.H.No. 18, Mouza โ Pawangaon, Tah. โ Kamptee, District โ Nagpur; total admeasuring 28,000.00 Sq. Mtrs. The current registration for the aforementioned project is valid until 30-01-2025. We are seeking an extension of 5 years, proposing a revised completion date of 31-12-2030. - Reasons for Delay Despite our best efforts to adhere to the original timeline, the development of the layout was hindered by the following factors: โข Market Slowdown: The real estate market in the pawangaon region experienced a significant slowdown in sales over the past 4 years. This resulted in lower-than-expected receivables from allottees. โข Liquidity Constraints: Due to the sluggish sales velocity, the project faced a temporary liquidity crunch, which impacted the pace of on-site infrastructure development (roads, water lines, and electricity provisioning). - Current Status and Justification for Extension: We wish to inform the Authority that the primary obstacle funding has now been resolved. โข Fund Mobilization: We have successfully secured the necessary capital through internal accruals to ensure the uninterrupted completion of the remaining development work. โข Work Plan: With the funds now available, we have mobilized contractors to complete the pending internal infrastructure. We estimate that the remaining work will be completed within the requested extension period. - Commitment to Allottees We remain committed to delivering the plots to our allottees with all promised amenities. We have kept our existing buyers informed regarding the progress and the reasons for this delay. We request you to kindly grant us the extension to enable us to complete the project as per the standards prescribed by MahaRERA.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Feb 2023
- Plot / CTS / survey no.
- 187/1/1/1
- Planning authority
- Nagpur Metropolitian Development Authority
- Approved layout land
- 28,000 sq.m
- Land for this registration
- 28,000 sq.m
- Recreational open space
- 2,650.29 sq.m
- Permissible built-up area
- 0 sq.m
- Promoter contact
- Raju Itkelwar
- Registered office
- N.K.Y tower
- North
- 18M wide Road
- South
- Shivdhura
- East
- 187-1-1-B
- West
- 187-3
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- ICICI BANK LIMITED โ 62086IFSC ICIC0000059Shriram tower kingsway sadar nagpur
Commencement Certificate documents
- NA map.pdf
- NA map.pdf
Buyer community
Connect with other buyers and owners of Mangala Estate โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Mangala Estate. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.