SATYA KIRAN TOWER
PLOT NO 69 KH NO.106/1, ZINGABAI TAKLI, 440030
- Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P50500050521
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2024
- Construction
- 59.7% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Possession extension history
- EXT50500027590Revised to December 2026
To, The Hon’ble Authority, Maharashtra Real Estate Regulatory Authority (MahaRERA), Mumbai, Maharashtra Subject: Application for Extension of Project Registration for “SATYA KIRAN TOWER” (MahaRERA Reg. No. P50500050521). Respected Sir/Madam, I, Shri Anil S/o Satyapal Singh Panwar, Promoter of the real estate project “SATYA KIRAN TOWER” (MahaRERA Registration No. P50500050521), hereby submit this application seeking an extension of the project registration, which is presently valid up to 31st December 2024. The project has been delayed due to several unavoidable factors such as reduced inflow of funds, disruptions in cash flow, irregular labour availability, delays in obtaining necessary NOCs and approvals, supply chain issues affecting timely delivery of materials, escalation in construction costs, shortage of skilled subcontractors, and adverse weather conditions during critical phases of work. The need to maintain quality standards and comply with updated technical specifications has also contributed to the overall delay. In view of these circumstances, I request the Hon’ble Authority to kindly grant an extension of Twelve (12) months to the project registration under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. Upon completion of the pending works within the extended period, the Promoter shall promptly apply for the Completion Certificate. I affirm that the Promoter continues to comply with all statutory provisions and that the information furnished in this application is true and correct to the best of my knowledge and belief. Kindly consider this application favourably.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Apr 2023
- Floors
- 8
- Plot / CTS / survey no.
- PLOT NO 69 KH NO.106/1
- Planning authority
- Others
- Approved layout land
- 695.83 sq.m
- Land for this registration
- 695.83 sq.m
- Permissible built-up area
- 1,680.99 sq.m
- Promoter contact
- ANIL SATYAPALSINGH PANWAR
- Registered office
- SATA KIRAN TOWER
- North
- NALA
- South
- GR GOPAL AGRAWAL
- East
- 36 MT WIDE ROAD
- West
- COMPOUND WALL
Project bank account
The RERA-designated account this project's payments should go to — verify before wiring any money.
- AXIS BANK — 160037IFSC UTIB0000330LAKADGANJ NAGPUR
Commencement Certificate documents
- Building Permit_compressed.pdf
Buyer community
Connect with other buyers and owners of SATYA KIRAN TOWER — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet — start one and connect with the next buyer researching SATYA KIRAN TOWER. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.