SAI RAJWADA 21

MahaRERA P50500050900Caution

by AICD INFRAVENTURE

PLOT NO.249,CITY SURVEY NO.169, MOUZA- AMBAZARI, AMBAZARI, 440010

Official record
Sept 2026
Possession
81.8%
Built
0
Complaints
14
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Sept 2024, now proposed Sept 2026 per the RERA filing.

Official RERA facts

Registration
P50500050900
Status
New
Stage
Certificate Signed
Possession
September 2026originally September 2024
Construction
81.8% complete
Units sold
11 of 14

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Landowner

JAY RAMCHANDRA DEOTALE, VIJAY RAMCHANDRA DEOTALE, VIDYA SANJAY MUNGHATE

Possession extension history

  • EXT50500025040Revised to September 2025

    Due to unforeseen circumstances beyond our control, the completion certificate for the aforementioned project has been delayed from the concerned department. This delay has arisen due to pending approvals and administrative procedures.

  • EA02122518492Revised to September 2026

    Due to unforeseen circumstances beyond our control, the completion certificate for the aforementioned project has been delayed from the concerned department. This delay has arisen due to pending approvals and administrative procedures. Consent of more than 51% has been obtained. The Occupation Certificate (OC) was received on 30th September 2025. All construction work was completed by 30th September 2025. After obtaining the extension, we will apply for the change application, and thereafter, we will apply for completion.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Open Parkingdone

Building & registration

RERA registered
May 2023
Floors
8
Unit mix
14 res ยท 0 comm
Architect
DEVINE ARCHITECTS
Plot / CTS / survey no.
PLOT NO.249,CITY SURVEY NO.169, MOUZA- AMBAZARI
Planning authority
Nagpur Municipal corporation
Approved layout land
645.59 sq.m
Land for this registration
645.59 sq.m
Permissible built-up area
2,294.04 sq.m
Registered office
SAI RAJWADA
Plot boundaries
North
PLOT NO 248
South
LAND
East
18 MTRS WIDE ROAD
West
HILL
Parking
21 four-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • CANARA BANK โ€” 28974
    IFSC CNRB0000265
    GANDHI NAGAR, NAGPUR, MAHARASHTRA-440010

Commencement Certificate documents

  • RERA Commencement Certificate.pdf

Buyer community

Connect with other buyers and owners of SAI RAJWADA 21 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAI RAJWADA 21. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.