NIRALA GREEN WOODS
by Nirala Buildtech Private Limited
PLOT NO. 4, KH NO. 11/2, Nr. Government School, 441501
- Behind schedule. Possession is due Dec 2026 but construction is only at 37.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P50500052967
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 37.9% complete
- Units sold
- 22 of 336
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Oct 2023
- Floors
- 7
- Unit mix
- 324 res ยท 12 comm
- Plot / CTS / survey no.
- PLOT NO. 4, KH NO. 11/2
- Planning authority
- MHADA
- Approved layout land
- 9,100 sq.m
- Land for this registration
- 9,100 sq.m
- Recreational open space
- 917.04 sq.m
- Permissible built-up area
- 15,057.89 sq.m
- Registered office
- 2nd Floor
- North
- KH NO-4 INDUSTRIAL AREA
- South
- KH NO-15
- East
- EXISTING 9 MTR ROAD KH NO-12
- West
- KH NO-10
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- IDBI BANK โ 60082IFSC IBKL0001811IDBI BANK SECTOR 55
Commencement Certificate documents
- MHADA COMMENCEMENT.pdf
- CC COMPLETION INTIMIDATION.pdf
- FINAL CC INTIMIDATION PDF.pdf
Buyer community
Connect with other buyers and owners of NIRALA GREEN WOODS โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching NIRALA GREEN WOODS. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.