PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

CHANAKYA APARTMENT

MahaRERA P50500056321Caution

by ASHISH NERKAR

Plot No 341, CSN 574, Mouje Ajani, Mouje Ajani, 440022

Official record
Dec 2027
Possession
45.8%
Built
0
Complaints
18
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Dec 2025, now proposed Dec 2027 per the RERA filing.

Official RERA facts

Registration
P50500056321
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2025
Construction
45.8% complete
Units sold
2 of 18

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Landowner

Yogesh Nilkanth Pathak, Pramod Hedau, Mrudula Hedau, Harnarayan Jaiswal, Rahul Panat, Ranganathan Ramratnam, Noopur Jumle, Sunita Sanjay Nasery, Brijbala Hemant Diddee, Hemant Diddee, Shirish Shivram Desai

Possession extension history

  • EA05082502314Revised to December 2027

    1. Late Actual Start of Construction due to Monsoon (June 2024 โ€“ November 2024) Although the project planning and preliminary work had commenced earlier, the actual on-site construction work started towards the end of June 2024. Immediately thereafter, the monsoon season began, lasting approximately 4 months, until November 2024. Due to continuous rainfall: Excavation and foundation activities were severely affected Workability on-site was restricted Safety considerations prevented regular execution of tasks 2. Waterlogging of Excavated Areas During Monsoon During rainy months, the excavated pits repeatedly filled with rainwater, causing: Delays in dewatering operations Difficulty in carrying out foundation works Repeated halts in structural activities This further pushed the construction timeline ahead. 3. Labour Shortage and Contractor Issues The contractor appointed for the project faced persistent labour availability issues. Even though payments were regularly released to the contractor, the work progressed at a very slow pace. Additionally, due to labour shortages, the site activities were halted multiple times, significantly impacting scheduled timelines for RCC and other civil works. 4. Delay Due to NMC NOC for Drainage Line Passing Through the Plot A drainage line was found to be passing through the project plot, which required clearance and permission from the Nagpur Municipal Corporation (NMC) before further construction could proceed. The process of obtaining: NOC, Technical clearance, Site verification and approval took longer than expected. This mandatory compliance requirement resulted in unavoidable delay in further progress of the project.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
May 2024
Floors
7
Unit mix
18 res ยท 0 comm
Architect
ARVIND RAJE AND ASSOCIATES
Plot / CTS / survey no.
Plot No 341, CSN 574, Mouje Ajani
Planning authority
Nagpur Municipal Corporation
Approved layout land
579.6 sq.m
Land for this registration
579.6 sq.m
Permissible built-up area
1,847.13 sq.m
Promoter contact
ASHISH NERKAR
Registered office
ASHISH NERKAR
Plot boundaries
North
9 MTRS WIDFE ROAD
South
LAND AND PROPERTYOF SHRI KEDAR
East
ABHINAV RESIDENCY
West
HOUSE OF SHRI MOGHE
Parking
11 four-wheeler46 two-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • ICICI BANK LIMITED โ€” 63825
    IFSC ICIC0001866
    NEAR AUDI SHOWROOM, SOMALWADA SQUARE, WARDHA ROAD, NAGPUR 440010

Commencement Certificate documents

  • BUILDING PERMIT.pdf

Buyer community

Connect with other buyers and owners of CHANAKYA APARTMENT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching CHANAKYA APARTMENT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.