GREENFIELD-5
by L G DEVELOPERS AND BUILDERS
309/37, 38, 39, 40, 42, 43, 44, 45, 46, HINGNA, 441110
- Behind schedule. Possession is due Mar 2027 but construction is only at 18.2%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.
Official RERA facts
- Registration
- P50500080606
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027
- Construction
- 18.2% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Jun 2025
- Floors
- 2
- Plot / CTS / survey no.
- 309/37, 38, 39, 40, 42, 43, 44, 45, 46
- Planning authority
- NAGAR PARISHAD, WANADONGRI
- Approved layout land
- 1,348.26 sq.m
- Land for this registration
- 1,348.26 sq.m
- Recreational open space
- 0 sq.m
- Permissible built-up area
- 1,654.29 sq.m
- Registered office
- GREENFIELD
- North
- ROAD
- South
- ROAD
- East
- ROAD
- West
- ROAD
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- FEDERAL BANK โ 45981IFSC FDRL0001848SHOP NO 5,6,7 & 8 ,TOWER 6, LAKE VIEW ENCLAVE ATOMIC ENERGY ROAD, AMRAVATI ROAD, WADI
Commencement Certificate documents
- Building Permit.pdf
Buyer community
Connect with other buyers and owners of GREENFIELD-5 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching GREENFIELD-5. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.