๐Ÿ—๏ธ
Under construction

MAHALAXMI APPARTMENTMahaRERA P51000015251

by SHALIK MAHADEORAO URKUDE

PLOT 2/3/23, NEAR DR MUNJE, 445304

May 2019
Possession
9.2%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (May 2019) has passed with construction at 9.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due May 2019 per the RERA filing.

Official RERA facts

Registration
P51000015251
Status
New
Stage
Certificate Signed
Possession
May 2019
Construction
9.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Feb 2018
Floors
4

Buyer community

Connect with other buyers and owners of MAHALAXMI APPARTMENT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MAHALAXMI APPARTMENT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.