Under construction

krishnakunj phase-IIMahaRERA P51400019951

by Krishna developr

14277/106, NEAR MANTHA CHOUK, 431203

Jun 2022
Possession
77.3%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 77.3%.

Official RERA facts

Registration
P51400019951
Status
New
Stage
Certificate Signed
Possession
June 2022
Construction
77.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths90%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drains50%
Landscaping & Tree Planting90%
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone

Building & registration

RERA registered
Mar 2019
Floors
6

Buyer community

Connect with other buyers and owners of krishnakunj phase-II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching krishnakunj phase-II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.