PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

VIGHNAHARTAMahaRERA P51500016039

by DEVGIRI CONSTRUCTION

214, CIDCO WALUJ MAHANAGAR 1, 431001

Mar 2023
Possession
0%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2023) has passed with construction at 0%.

Official RERA facts

Registration
P51500016039
Status
New
Stage
Certificate Signed
Possession
March 2023
Construction
0% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Internal Roads & Footpathsnot started
Internal Roads & Footpathsnot started
Internal Roads & Footpathsnot started
Internal Roads & Footpathsnot started
Water Supplynot started
Water Supplynot started
Water Supplynot started
Water Supplynot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Street Lightingnot started
Street Lightingnot started
Street Lightingnot started
Street Lightingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Solid Waste Management And Disposalnot started
Solid Waste Management And Disposalnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Water conservation /Rain water harvestingnot started
Water conservation /Rain water harvestingnot started
Water conservation /Rain water harvestingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Fire protection and fire safety requirementsnot started
Fire protection and fire safety requirementsnot started
Fire protection and fire safety requirementsnot started
Fire protection and fire safety requirementsnot started

Building & registration

RERA registered
Apr 2018
Floors
7

Buyer community

Connect with other buyers and owners of VIGHNAHARTA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VIGHNAHARTA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.