UNITY PARKMahaRERA P51500024945

by BAHETI LANDMARK

GUT NO 94, NEAR MAHADA, 431136

Jan 2027
Possession
76.9%
Built
0
Complaints
45
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Jan 2027 per the RERA filing.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jan 2027 per the RERA filing.

Official RERA facts

Registration
P51500024945
Status
New
Stage
Certificate Signed
Possession
January 2027originally December 2024
Construction
76.9% complete
Units sold
22 of 45

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Mar 2020
Floors
4
Unit mix
45 res ยท 0 comm

Buyer community

Connect with other buyers and owners of UNITY PARK โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching UNITY PARK. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.