18 LAXMI ELITESMahaRERA P51500055205
GAT NO 214 PLOT NO 80,81,82,83,86,87,88,89, SATARA PARISAR, 431010
- Behind schedule. Possession is due Dec 2026 but construction is only at 11.8%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P51500055205
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 11.8% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Mar 2024
- Floors
- 3
- Plot / CTS / survey no.
- GAT NO 214 PLOT NO 80,81,82,83,86,87,88,89
- Planning authority
- CHATRPATI SAMBHAJI NAGAR MUNICIPAL CORPORATION
- Approved layout land
- 1,080 sq.m
- Land for this registration
- 1,080 sq.m
- Permissible built-up area
- 1,900.8 sq.m
- Registered office
- WELCOME NAGAR
- North
- PLOT NO 84 85
- South
- PLOT NO 79 90
- East
- 6 MTR WIDE ROAD
- West
- 6 MTR WIDE ROAD
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- KOTAK MAHINDRA BANK LIMITED โ 84901IFSC KKBK0000693Kandi Tower, CTS No 12995, Jalna Road, Aurangabad, Maharashtra 431001
Commencement Certificate documents
- Building Permission_Commencement Letter.pdf
Buyer community
Connect with other buyers and owners of 18 LAXMI ELITES โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching 18 LAXMI ELITES. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.