Nayantara Presidency Phase 4MahaRERA P51600000098
by Pancharatna Builcon Pvt. Ltd
881/1A/1, Rajiv nagar, 422002
Mar 2028
Possession
69.5%
Built
1
Complaints
112
Units
High risk
- Possession delayed ~4 yrs. Originally promised Mar 2024, now proposed Mar 2028 per the RERA filing.
Official RERA facts
- Registration
- P51600000098
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2028originally March 2024
- Construction
- 69.5% complete
- Units sold
- 9 of 112
RERA complaint record1 record
- ComplaintSM1250008611 Aug 2025Ram G vs Pancharatna Builcon Pvt. LtdCase No SM12500086.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths20%
Water Supply10%
Sewerage (Chamber, Lines, Septic Tank , STP)10%
Storm Water Drains50%
Landscaping & Tree Planting50%
Street Lighting50%
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Jun 2017
- Floors
- 16
- Unit mix
- 112 res ยท 0 comm
- Architect
- Dinesh Bhamre
Buyer community
Connect with other buyers and owners of Nayantara Presidency Phase 4 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Nayantara Presidency Phase 4. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.