Anmol Nayantara City One Phase 1MahaRERA P51600000539

by Bafna Realtors Pvt Ltd

785/ 1 2 3/1 ,785/1 2 3/6,785/1 2 3/3/3,785/1 2 3/3/1,778/1C,778/2B P,785/1 2 3/9,784/2,785/1 2 3/1, Nashik, 422008

Dec 2018
Possession
79.6%
Built
1
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2018) has passed with construction at 79.6%.

Official RERA facts

Registration
P51600000539
Status
Ongoing
Stage
Certificate Signed
Possession
December 2018
Construction
79.6% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)85%
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Water50%
Solid Waste Management And Disposal10%
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements80%
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone

Building & registration

RERA registered
Jul 2017
Floors
15

Buyer community

Connect with other buyers and owners of Anmol Nayantara City One Phase 1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Anmol Nayantara City One Phase 1. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.