All RERA projects
๐๏ธ
Under construction
The Metrozone Athens A2MahaRERA P51600005464
by Sanklecha Construction Private Limited
Survey No 7/1 to 5 and 8/1 to 5, INDIRA NAGAR, 422009
Oct 2022
Possession
90.9%
Built
10
Complaints
0
Units
High risk
- Possession delayed ~4 yrs. Originally promised Sept 2018, now proposed Oct 2022 per the RERA filing.
- 10 RERA complaints. 10 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Oct 2022) has passed with construction at 90.9%.
Official RERA facts
- Registration
- P51600005464
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- October 2022originally September 2018
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record10 records
- ComplaintCC00100000008040531 Oct 2023Puneet Ajit Sanklecha vs Bhisham Kapoor
- ComplaintCC00100000008040431 Oct 2023Puneet Ajit Sanklecha vs Bhisham Kapoor
- ComplaintCC00100000006034124 Jul 2023Puneet Ajit Sanklecha vs KOODANDI MOHANDAS AND MAHALXMI MOHANDAS
- Misc. applicationCC0010000000001031 May 2019MRS. KRITIKA KARAMCHANDANI, MR. SANJEET KARAMCHANDANI vs M/S SANKLECHA CONSTRUCTIONS PVT. LTD, MR VINAYAK K. SANKLECHA, MR. ANWAR HUSSAIN J. THIM103.pdf on MahaRERA
- ComplaintCC0010000000001031 May 2019MRS. KRITIKA KARAMCHANDANI, MR. SANJEET KARAMCHANDANI vs M/S SANKLECHA CONSTRUCTIONS PVT. LTD, MR VINAYAK K. SANKLECHA, MR. ANWAR HUSSAIN J. THIM103.pdf on MahaRERA
- ComplaintCC00100000000007910 Dec 2018Shirish Patankar vs Sanklecha Constructions Pvt.Ltd.79 final dismissal order dt 16-04-19.pdf on MahaRERA
- ComplaintCC0010000000000606 Jun 2018Jitendra Vaidya vs sanklecha constructions pvt ltd.ilovepdf_merged (3).pdf on MahaRERA
- Misc. applicationCC0010000000000606 Jun 2018Jitendra Vaidya vs sanklecha constructions pvt ltd.ilovepdf_merged (3).pdf on MahaRERA
- Misc. applicationCC00100000000000726 Oct 2017Manoj Ram Hardasani vs Sanklecha Constructions Pvt Ltdswapnil scan_001-83-84.pdf on MahaRERA
- ComplaintCC00100000000000726 Oct 2017Manoj Ram Hardasani vs Sanklecha Constructions Pvt Ltdswapnil scan_001-83-84.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths70%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone
Building & registration
- RERA registered
- Aug 2017
- Floors
- 14
Buyer community
Connect with other buyers and owners of The Metrozone Athens A2 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching The Metrozone Athens A2. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.