YOGMALA APPARTMENT WING B

MahaRERA P51600006719High risk

by SWASTIK ESTATES

22B / 22A/ 2B/ 33, 34, Jail Road, 422101

Official record
Dec 2021
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2019, now proposed Dec 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 90.9%.

Promoter

Builder profile

Builder
SWASTIK ESTATES

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600006719
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021originally December 2019
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Aug 2017
Floors
5

Buyer community

Connect with other buyers and owners of YOGMALA APPARTMENT WING B — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching YOGMALA APPARTMENT WING B. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.