YOGMALA APPARTMENT WING B
22B / 22A/ 2B/ 33, 34, Jail Road, 422101
- Possession delayed ~2 yrs. Originally promised Dec 2019, now proposed Dec 2021 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 90.9%.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51600006719
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2021originally December 2019
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Aug 2017
- Floors
- 5
Buyer community
Connect with other buyers and owners of YOGMALA APPARTMENT WING B — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet — start one and connect with the next buyer researching YOGMALA APPARTMENT WING B. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.