Atmamalik ApartmentMahaRERA P51600010688
by Hrishita Buildcon & Infrastructures Pvt. Ltd.
Survey No.66/A/1 plot no 14.CTS no2015, chunchale, Shiwar, nashik, Shiwar, 422010
- Possession delayed ~3 yrs. Originally promised Dec 2018, now proposed Dec 2021 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 55.2%.
Official RERA facts
- Registration
- P51600010688
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2021originally December 2018
- Construction
- 55.2% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Aug 2017
- Floors
- 6
Buyer community
Connect with other buyers and owners of Atmamalik Apartment โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Atmamalik Apartment. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.