RENUKA ESTATE PHASE 1MahaRERA P51600016228
Survey No. 1529+1554+1556, Shinde, 422102
Dec 2028
Possession
27.3%
Built
0
Complaints
120
Units
High risk
- Possession delayed ~8 yrs. Originally promised May 2021, now proposed Dec 2028 per the RERA filing.
Official RERA facts
- Registration
- P51600016228
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2028originally May 2021
- Construction
- 27.3% complete
- Units sold
- 21 of 120
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply70%
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started
Building & registration
- RERA registered
- Apr 2018
- Floors
- 6
- Unit mix
- 96 res ยท 24 comm
Buyer community
Connect with other buyers and owners of RENUKA ESTATE PHASE 1 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching RENUKA ESTATE PHASE 1. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.