AADINATH TOWERMahaRERA P51600018248
442/1/B, A/P PIMPALGAON ,TAL-NIPHAD,DIST-NASHIK, 422209
Sept 2023
Possession
40%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Sept 2023) has passed with construction at 40%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2023 per the RERA filing.
Official RERA facts
- Registration
- P51600018248
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2023
- Construction
- 40% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Internal Roads & Footpathsnot started
Water Supplynot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Open Parkingnot started
Building & registration
- RERA registered
- Oct 2018
- Floors
- 5
Buyer community
Connect with other buyers and owners of AADINATH TOWER โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching AADINATH TOWER. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.