Under construction

MONSOON MISTMahaRERA P51600019135

by NITIN DAYALAL KOTHARI

279-1-2, 30, 35-C-P/1, Igatpuri, 422402

Dec 2024
Possession
81.8%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~5 yrs. Originally promised Mar 2020, now proposed Dec 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 81.8%.

Official RERA facts

Registration
P51600019135
Status
New
Stage
Certificate Signed
Possession
December 2024originally March 2020
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone
Liftdone

Building & registration

RERA registered
Jan 2019
Floors
5

Buyer community

Connect with other buyers and owners of MONSOON MIST โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MONSOON MIST. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.