SHREE ATHARV PARK PHASE-IIIMahaRERA P51600021832

by ATHARVASHREE BUILDMAT PRIVATE LIMITED

SURVEY NO 30/3/2/1, PLOT NO 1/2/3/4, APMC NAMCO CANCER HOSPITAL, 422003

Dec 2024
Possession
81.8%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 81.8%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2024 per the RERA filing.

Official RERA facts

Registration
P51600021832
Status
New
Stage
Certificate Signed
Possession
December 2024
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving station50%
Open Parking80%

Building & registration

RERA registered
Jul 2019
Floors
8

Buyer community

Connect with other buyers and owners of SHREE ATHARV PARK PHASE-III โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHREE ATHARV PARK PHASE-III. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.