Under construction

TREELAND PHASE - 3MahaRERA P51600025197

by ABH DEVELOPERS PRIVATE LIMITED

Hissa No. 5,6 and 9 of S.No. 21/1 and 3, 24, 25/1, 25/2, 167, 28/1/2/1, 28/1/2/2 and 26/1, GANGAPUR ROAD, 422025

Mar 2028
Possession
49.3%
Built
0
Complaints
47
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P51600025197
Status
New
Stage
Certificate Signed
Possession
March 2028
Construction
49.3% complete
Units sold
28 of 47

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Community Buildings90%
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposal60%
Water conservation /Rain water harvestingdone
Energy managemcnt60%
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parking60%

Building & registration

RERA registered
Mar 2020
Floors
26
Unit mix
46 res ยท 1 comm

Buyer community

Connect with other buyers and owners of TREELAND PHASE - 3 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching TREELAND PHASE - 3. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.