Under construction
JAGANNATH RESIDENCYMahaRERA P51600027274
GUT NO 17/2 PLOT NO 3,4,5 MAPARWADI SHIWAR, BEHIND JINDAL HOUSING, 422113
Dec 2026
Possession
90.9%
Built
0
Complaints
62
Units
High risk
- Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Dec 2026 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P51600027274
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2022
- Construction
- 90.9% complete
- Units sold
- 31 of 62
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationdone
Building & registration
- RERA registered
- Dec 2020
- Floors
- 2
- Unit mix
- 62 res ยท 0 comm
Buyer community
Connect with other buyers and owners of JAGANNATH RESIDENCY โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching JAGANNATH RESIDENCY. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.