KALAPURNAM PARKMahaRERA P51600031631

by DINKAR MURLIDHAR PALDE

Survey No -29/1/2/3/9A -19B-10/10B/12/7, Deolali Cantonment Board Nashik, 422401

Jul 2026
Possession
56.2%
Built
0
Complaints
0
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2026 per the RERA filing.

Official RERA facts

Registration
P51600031631
Status
New
Stage
Certificate Signed
Possession
July 2026
Construction
56.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Nov 2021
Floors
5

Buyer community

Connect with other buyers and owners of KALAPURNAM PARK โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching KALAPURNAM PARK. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.