AMRUT AROMAMahaRERA P51600032882

by ABHINAV PRAKASH AMRUTKAR

PLOT NO 21 AND 23 OF S.NO./G.NO.17/A17/B22/2/1D22/2/1A/1, PLOT NO 21+23 S.NO. 17/A+17/B+22/2/1D+22/2/1A/1, KAMATHWADE ROAD, NEAR MAULI LAWNS, SAPTASHRUNGI NAGAR, KAMATWADE, 422010

Dec 2024
Possession
90.9%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 90.9%.

Official RERA facts

Registration
P51600032882
Status
New
Stage
Certificate Signed
Possession
December 2024
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Feb 2022
Floors
7

Buyer community

Connect with other buyers and owners of AMRUT AROMA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AMRUT AROMA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.