PropPin
Caution
  • Possession date passed. The proposed possession date (Jul 2023) has passed with construction at 60.5%.

Promoter

Builder profile

Builder
Gangaprassad Shivprasad Sharma

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51600047433
Status
New
Stage
Certificate Signed
Possession
July 2023
Construction
60.5% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.