Under construction

MAHADEV APARTMENTMahaRERA P51600047552

by UMIYAKRIPA BUILDCON

SR.NO/G.NO.239/1A/1/1/11, PLOT NO.11, MHASRUL SHIWAR, NASHIK, 422004

Mar 2025
Possession
90.9%
Built
0
Complaints
18
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2025) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2025 per the RERA filing.

Official RERA facts

Registration
P51600047552
Status
New
Stage
Certificate Signed
Possession
March 2025
Construction
90.9% complete
Units sold
17 of 18

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Nov 2022
Floors
7
Unit mix
18 res ยท 0 comm
Architect
SURESH N MAVANI
Plot / CTS / survey no.
SR.NO/G.NO.239/1A/1/1/11, PLOT NO.11
Planning authority
NASHIK MUNICIPAL CORPORATION
Approved layout land
472.5 sq.m
Land for this registration
472.5 sq.m
Permissible built-up area
1,508.78 sq.m
Registered office
SHIV PALACE APT
Plot boundaries
North
9 MTR WIDE ROAD
South
ADJ S NO 239 PART
East
ADJ PLOT NO 10
West
ADJ S NO 238
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • THE COSMOS CO OPERATIVE BANK LIMITED โ€” 40403
    IFSC COSB0000910
    UMIYA SHAKTI CO OP HSG SOC S NO 471 BANKAR CHOWK KATHE LANE DWARKA NASHIK 422011

Commencement Certificate documents

  • CC UB.pdf

Buyer community

Connect with other buyers and owners of MAHADEV APARTMENT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MAHADEV APARTMENT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.