MAHALAXMI GLORY APARTMENT
by DEVENDRA VISHWASRAO SONAWANE
PLOT NO 13 AND 14 OF S.NO 244/10/12, RASBIHARI MERI LINK ROAD, NEXT TO RASBIHARI SCHOOL PANCHAVATI NASHIK, 422003
- Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 90.9%.
Official RERA facts
- Registration
- P51600049937
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2025
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Mar 2023
- Floors
- 7
- Plot / CTS / survey no.
- PLOT NO 13 AND 14 OF S.NO 244/10/12
- Planning authority
- Others
- Approved layout land
- 403.13 sq.m
- Land for this registration
- 403.13 sq.m
- Recreational open space
- 0 sq.m
- Permissible built-up area
- 1,296.84 sq.m
- Promoter contact
- DEVENDRA VISHWASRAO SONAWANE
- Registered office
- ASHIRWAD GLORY
- North
- PLOT NO 15
- South
- COLONY ROAD 9 MTR
- East
- PLOT NO 11 AND 12
- West
- COLONY ROAD 7 MTR PROPOSED 9 MTR
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- AXIS BANK โ 160647IFSC UTIB0001041GANGAPUR ROAD NASHIK
Commencement Certificate documents
- Scan commencement.pdf
Buyer community
Connect with other buyers and owners of MAHALAXMI GLORY APARTMENT โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching MAHALAXMI GLORY APARTMENT. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.