Under construction

Aanandam City

MahaRERA P51600052616High risk

by Swapnil Anil Mogal

Plot No 2 of CTS 219/3/1/2 at Deolali Shiwar, Nashik 422214, Sinnar Phata, 422214

Official record
Dec 2026
Possession
83.8%
Built
1
Complaints
32
Units
High risk
  • Possession delayed ~1 yr. Originally promised Jul 2025, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51600052616
Status
New
Stage
Certificate Signed
Possession
December 2026originally July 2025
Construction
83.8% complete
Units sold
28 of 32

RERA complaint record1 record

  • ComplaintCC1260394225 Jun 2026
    sagar mahadan nistane vs Swapnil Anil Mogal

Landowner

Vijay Kisan Gadekar

Possession extension history

  • EA04072501956Revised to December 2025

    We have applied for an extension because we submitted an application for the Occupancy Certificate (OC) to the Corporation, which will take some time to process. Therefore, we kindly request an extension until 31st December 2025.

  • EA31122519205Revised to June 2026

    The project is impacted by financial constraints, and there is a shortage of labor required to complete the work

  • EA26062621562Revised to December 2026

    The construction of the project could not be completed within the originally approved registration period due to a combination of factors beyond the reasonable control of the Promoter. The progress of construction was affected by delays in obtaining statutory approvals and NOCs from the concerned authorities, changes and revisions in sanctioned plans, intermittent shortage of labour and construction materials, financial constraints arising from market conditions, and other unavoidable circumstances impacting the execution schedule.The Promoter has continued to undertake construction activities and is committed to completing the remaining work at the earliest. The extension sought is solely for the purpose of completing the balance construction, obtaining the Occupancy Certificate/Completion Certificate, and fulfilling all obligations under the provisions of the Real Estate (Regulation and Development) Act, 2016.The Promoter undertakes to complete the project within the extended period sought and shall comply with all applicable provisions of the Act and the Rules framed thereunder.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Sept 2023
Floors
2
Unit mix
32 res ยท 0 comm
Architect
Ar Nikhil Nandkumar Gaikwad
Plot / CTS / survey no.
Plot No 2 of CTS 219/3/1/2 at Deolali Shiwar, Nashik 422214
Planning authority
Nashik Municipal Corporation, Nashik
Approved layout land
4,000 sq.m
Land for this registration
4,000 sq.m
Permissible built-up area
3,643.75 sq.m
Promoter contact
Swapnil Anil Mogal
Registered office
Nice Sankul
Plot boundaries
North
30 Meter Wide Road
South
City Survey No 8871
East
Remaining part of City Survey No 8750
West
Remaining part of City Survey No 8750
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • AXIS BANK โ€” 162253
    IFSC UTIB0002656
    Ground Floor, Shop No 8, Suyojit Arcade, Nashik Pune Road, Nashik, Maharashtra Pin 422011

Commencement Certificate documents

  • CC .pdf

Buyer community

Connect with other buyers and owners of Aanandam City โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Aanandam City. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.