SIDDHIVINAYAK TOWN SQUARE
GAT NO.55/1/B, MORE NAGAR, 423301
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P51600053976
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027
- Construction
- 12.7% complete
- Units sold
- 0 of 91
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Dec 2023
- Floors
- 8
- Unit mix
- 50 res ยท 41 comm
- Architect
- BHARAT M SINNARKAR
- Plot / CTS / survey no.
- GAT NO.55/1/B
- Planning authority
- Office of the Sub-Divisional Officer, Baglan
- Approved layout land
- 4,000 sq.m
- Land for this registration
- 4,000 sq.m
- Permissible built-up area
- 5,408.62 sq.m
- Registered office
- SARAF BAZAR
- North
- AREA OF SUKADEV SONAWANE
- South
- KANDHANA ROAD
- East
- SATAN DEVALA ROAD
- West
- GAT NO 55-1 REMAINING BOUDRY OF BALU AHIRE
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- IDBI BANK โ 59848IFSC IBKL0001570SHOP NO 15-18 KT COMPLEX KT BAGAD NAGAR SATANA BAGLAN 423301
Commencement Certificate documents
- Revised_Commencement Certificate.pdf
Buyer community
Connect with other buyers and owners of SIDDHIVINAYAK TOWN SQUARE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SIDDHIVINAYAK TOWN SQUARE. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.