SAI KUBER PROJECT
by SAI KUBER BUILDERS AND DEVELOPERS
PLOT NO 3 SURVEY NO 49(48)/7/A/2, DESHWANDI, 422103
- Behind schedule. Possession is due Dec 2026 but construction is only at 33.6%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P51600077676
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 33.6% complete
- Units sold
- 0 of 15
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Oct 2024
- Floors
- 2
- Unit mix
- 11 res ยท 4 comm
- Plot / CTS / survey no.
- PLOT NO 3 SURVEY NO 49(48)/7/A/2
- Planning authority
- SINNAR MUNICIPAL COUNCIL
- Approved layout land
- 984.16 sq.m
- Land for this registration
- 984.16 sq.m
- Recreational open space
- 0 sq.m
- Permissible built-up area
- 996.37 sq.m
- Registered office
- VISHWANATH APARTMENT
- North
- SURVEY NO 49 7 B
- South
- 18 MTR DP ROAD
- East
- SURVEY NO 49 7 A 1
- West
- PLOT NO 1 AND 2
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- ICICI BANK LIMITED โ 62161IFSC ICIC0000182ICICI Bank Ltd., Sai Plaza, Near Bytco College, Nashik Road, Nashik.422101
Commencement Certificate documents
- Comencement certificate.pdf
Buyer community
Connect with other buyers and owners of SAI KUBER PROJECT โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SAI KUBER PROJECT. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.