UMIYA ARCADE WING A AND B

by UMIYA CONSTRUCTION COMPANY

105/2, 3, 15, Titwala, 421605

Apr 2018
Possession
60.9%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Apr 2018) has passed with construction at 60.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2018 per the RERA filing.

Official RERA facts

Registration
P51700002949
Status
Ongoing
Stage
Certificate Signed
Possession
April 2018
Construction
60.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths10%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvesting10%
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2017
Floors
7

Buyer community

Connect with other buyers and owners of UMIYA ARCADE WING A AND B โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching UMIYA ARCADE WING A AND B. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.