Under construction

Irasa Greens

by SUBURBAN SPACES LLP

Survey No 124 Hissa No 3A Survey No 124 Hissa No 3B Survey No 125 Hissa No 1P, Village Dohole, 421302

Dec 2027
Possession
15.2%
Built
0
Complaints
187
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2023, now proposed Dec 2027 per the RERA filing.

Official RERA facts

Registration
P51700005934
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally December 2023
Construction
15.2% complete
Units sold
25 of 187

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Planting75%
Street Lightingnot started
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
5
Unit mix
176 res ยท 11 comm

Buyer community

Connect with other buyers and owners of Irasa Greens โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Irasa Greens. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.