Under construction

Rosa Oasis Phase 3

by Uma Enterprises

s.no. 124/2/3, 125/2, 125/3/1, 125/3/2, 125/4 and 125/5, Thane, 400615

High risk
  • Possession date passed. The proposed possession date (Dec 2017) has passed with construction at 90.9%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2017 per the RERA filing.

Official RERA facts

Registration
P51700006155
Status
Ongoing
Stage
Certificate Signed
Possession
December 2017
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Energy managemcntnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parking50%

Building & registration

RERA registered
Aug 2017
Floors
23

Buyer community

Connect with other buyers and owners of Rosa Oasis Phase 3 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Rosa Oasis Phase 3. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.