PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

vihang valley

by VIHANG INFRASTRUCTURE PVT LTD

74/1/1,74/1/2, 74/1/3, 74/2/A, 2/B, 3,4,5 75/1,2, 72/4, 77/1,2,3 69/1,3a,4,5,6 78/1A,1B,3A,3B,4,, Thane, 400601

Dec 2026
Possession
66.5%
Built
50
Complaints
0
Units
High risk
  • 50 RERA complaints. 50 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51700007077
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026
Construction
66.5% complete
Units sold
0 of 0

RERA complaint record50 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
24

Buyer community

Connect with other buyers and owners of vihang valley โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching vihang valley. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.